Back to Resumes List

E&I Inspector

Objective


Dear Sir/Mdm,

Good Evening.This is from S.Raja(38 YEARS).Singapore P.R.I am an Electronics&Instrumentation Engineer.I have more than 9 years experience in marine fields.Currently i am in Transocean as an E&I Supervisor & inspector position under contract basis.Now i am looking for suitable E&I Inspector Position in singapore.Here i attached my UP-DATED RESUME for your kind consideration.If you want any further details,pls call me.Thanks.



Best Regards,



S.Raja


Experience


PROFESSIONAL EXPERIENCES:



Project Undertaken:



Company : TRANSOCEAN (June 2008 to Till now)



Project : SEDCO 706-DP Conversion & Upgrade project

KEPPEL FELS. Singapore.

Designation : E&I SUPERVISOR & INSPECTOR



Responsibilities:



Responsible of E&I installation & inspection activities on the Site.

Installation & inspection of instruments and electrical equipments and panels.

Supervise the quality control function on site.

Issuing, follow up and approval of NCR and MRs.

Inspect Electrical&Instrumental Work carried out by the yard.

Conducting different tests such as line check& loop tests carried out by the Yard.

Monitoring, review and inspection of all major activities and progress of the E&I construction works.

Interface with engineering, planning and procurement as well as other disciplines.



Project Undertaken:



Company : Bluewater Energy (August 2007 to May 2008)



Project : Aoki Mizu.FPSO Conversion

Sembawang Singapore.

Designation : SENIOR E&I INSPECTOR (ATEX)



Responsibilities:

• Inspect and list all the equipment installed in hazardous zones

• Review maintenance records to highlight any problems

• Conduct an ignition hazard assessment on non-electrical equipment

• Assess the electrical equipment with respect to its certification

• Record your findings in a report or file

• Implement any corrective action arising

Responsible of E&I installation & inspection activities on the Site.

Installation & inspection of instruments and electrical equipments and panels.

Supervise the quality control function on site.

Issuing, follow up and approval of NCR and MRs.

Inspect Electrical&Instrumental Work carried out by the yard.

Conducting different tests such as line check& loop tests carried out by the Yard.

Monitoring, review and inspection of all major activities and progress of the E&I construction works.

Interface with engineering, planning and procurement as well as other disciplines.



Project undertaken:



Company : NEPTUNE MARINE OIL&GAS LTD (Feb 2007 to July 2007)



Project : Neptune Explorer-Rig upgrading project

Sembawang Singapore.

Designation : Construction Engineer(E&I)

Customer : RELIANCE, India.



Responsibilities:



Responsible for Instrument Construction activities on the Site.

Installation & inspection of power distribution equipments such as Transformer and panels.

Contact Point with the Yard Construction Managers & Supervisor as well as Area Manager. Issuing, follow up and approval of Work Order and MRs.

Inspect Instrumental Work carried out by the yard.

Survey different tests as loop tests, etc carried out by the Yard.

Monitoring, review, inspection and report all major activities and progress of the instrument construction works.

Interface with engineering, planning and procurement as well as other disciplines.



Project Undertaken:



Company : TRANSOCEAN (Feb 2006 to Jan 2007)



Project : SEDCO 702-DP Conversion & Upgrade project

KEPPEL FELS. Singapore.

Designation : SENIOR E&I INSPECTOR



Responsibilities:

Responsible for E&I Inspection activities.

Inspection of materials as per project specifications.

Rectification action plan for generated punch.

Responsible for clearing punches with contractors.

Co-ordination with client & contractors...

Preparation of I.T.R sheets for E&I activities.



Project undertaken:



Company : SMOE (Feb 2005 to Dec 2005)



Project : ERHA- FPSO PROJECT

Sembawang.Singapore.

Designation : SENIOR QA/QC INSPECTOR

Client : SAIPEM



Responsibilities:



Responsible for E&I construction activities.

Inspection of materials as per project specifications.

Rectification action plan for generated punch.

Responsible for clearing punches with contractors.

Co-ordination with client & contractors attending safety co-ordination meeting.



Project Undertaken:



Company : MODEC (Sep 2004 to Jan 2005)



Project : SANTOS-MUTINEER/EXETER DEVELOPMENT PROJECT

Jurong Shipyard.Singapore.

Designation : E&I INSPECTOR



Responsibilities:



Ability to organize, lead, act as an E&I supervisor.

Responsible for Termination works, hot loop checks, Cold loop checks and Testing.

Instrument Calibration and Testing.

Preparation of ITR sheets for all E&I activities.

Rectification action plan for generated punch list and NCR.

Responsible for safety issue on sites.



Duration : July 2002 to Aug 2004.

Designation : Instrumentation Engineer

Employer : Factory System Pte Ltd, Singapore



Job Responsibilities:

Testing and maintaining of Control system for Shipyard Automation system.

Conducting failure investigation with client’s sub- contractors.

Analyzing System faults with Clients.

Provide Engineering supports and co-ordination with project team.



Project Undertaken:



Working as an Instrumentation Inspector in KBR (Barracuda Vessel Conversion Project) P43 MARTIMA (FPSO), Brazil at Jurong Shipyard Ltd.



Client: KBR



Responsibilities:

Inspection of construction activities, I/O Panels and Instruments.

Responsible for Termination works, hot loop checks, Cold loop checks and Testing.

Instrument Calibration and Testing.

Preparation of ITP and FTC sheets for all E&I activities.

Rectification action plan for generated punch list and NCR.



Duration : August 2001 to July 2002.

Designation : Instrumentation Engineer. (QA/QC)

Employer : Total Automation Ltd. Singapore.



Project undertaken:



WHITE TIGER WATER INJECTION MODULE FOR VIETO PRESTO Vietnam at Sembawang shipyard. Singapore.

Job Responsibility:



Monitoring the job progress.Conducting the inspection with clients. Monitoring the job quality.

Raise the I.T.R sheets & clear the punches. Attending safety meetings.



Module 1, 2 & 3: Water injection platform



Inspection, Testing and preparation of Check sheets for all E & I activities.

Inspection of Motors. (Make M/s Alstom):Motor configuration.Wiring inspection.Bus bar

Inspection & testing - Ductor test & MeggerTest.

Inspection of I/O Panels, Lighting Distribution Panels Battery Charger, UPS Panels.

Inspection of Fire & Gas Systems, a) Inspection of F & G Panels. b) Inspection Smoke.

Detectors, Heat Detectors, Gas Detectors & Manual Call Points.c)Inspection of CO2 Cabinets

to Control Panels & Terminations.

Rectification action plan for generated Punch List & NCR.

Inspection of lighting circuits.

Inspection of Impulse Tubing by conducting high Pressure test using Nitrogen & check for

leakage & Holding pressure.

Preparation of Check Sheets & Clearing Punch list &NCR.



Duration : November 1997 to August 2001

Designation : Assistant Engineer

Employer : Jurong Machinery Automation pte Ltd. Singapore.



Job Responsibility:

Responsible for instrument installation, termination, loop check &calibration. Monitoring the quality of jobs. Solving the site manpower issue. Preparation of job progress report & safety issue on site.


Education


EDUCATIONAL QUALIFICATIONS:



Bachelor of Electronics and Instrumentation Engineering, 1991 - 1995, Annamalai University, Tamilnadu, India.



Diploma in Electrical and Electronics Engineering, 1985-1988, State Education and Training, Madras, India.


Certification


SKILLS CERTIFICATES:



• Certificate on Comp”Ex”Competence Based Training in Hazardous Areas-ASSET



• Certificate in PLC Programming using Ladder Support Software (I.T.E Yishun, Singapore)



• Certificates in Shipyard Safety Supervisor Course (M.O.M, Singapore)


Skils


SKILLS:



1 Instruments Calibration and Installation works.

2 Materials take off list and cost estimation of Automation control and instrumentation system.

3 Preparations of technical specifications such as Pressure gauge, Pressure switch, Pressure transmitter, Level controller, Level Indicator, Temperature controller, Temperature transmitter and Temperature Indicator & control valves.

4 Preparation of Cable Scheduling and Junction Box details.

5 In charge of Cable laying, termination works and erection of Panels.



6 Installation Inspection 0f ship electrical system such as power distribution system,

fire and gas system, lighting system & communication system.(PAGA)

7 Inspection, testing and preparation of check sheets for all E&I activities.

8 Issuing, follow up and approval of Work Order, MRs & NCR.


 

Singapore, Singapore,
View Contact Information